New Detached ADU in Paradise: Timeline and Cost at a Glance
A new detached ADU in Paradise generally runs $45,000 – $130,000 and takes four to seven months from the first site visit to the final inspection. The wide spread comes down to size, whether you tie into the main house’s utilities or run separate service, and finish level. Call (844) 797-5026 and we’ll walk your lot and give you a real number instead of a per-square-foot guess.
How a New Detached ADU Gets Built in Paradise, Start to Finish

Detached means what it sounds like: a separate structure with its own foundation, its own roof, and its own four walls. That changes the order of work compared with a garage conversion, and it changes how long the county wants to look at things. Here’s the sequence we run.
Stage 1: Site walk and feasibility (week 1). We measure setbacks, check where the sewer lateral and water main run, and look at how water moves across your lot after a monsoon storm. You decide the footprint and where the unit sits relative to the main house. In Paradise this stage matters more than most places, because the desert drainage pattern on a lot often rules out a corner you liked on paper.
Stage 2: Plans and county submittal (weeks 2 – 6). Drafting runs three to four weeks. Then the plans go to Clark County, not to a city building department, and review typically takes four to six weeks depending on the queue. You approve the final layout and exterior finish before we submit. Nobody breaks ground until the permit is in hand.
Stage 3: Site prep and foundation (weeks 1 – 3 of construction). Grading, trenching for utilities, and either a slab or stem-wall foundation. You decide at this point whether the ADU taps the main house’s electrical panel or gets its own meter; that decision is much cheaper made now than after the slab cures. Concrete curing in summer heat is its own discipline here, and we schedule pours early morning for that reason.
Stage 4: Framing, roof, and rough-in (weeks 4 – 9). Walls up, roof dried in, then electrical, plumbing, and HVAC rough-in followed by the county’s framing and rough inspections. You pick windows and the exterior door around week 5, since those lead times affect when the shell closes. Impact-rated glazing is worth talking about at this stage, not later.
Stage 5: Finishes, final inspection, handover (weeks 10 – 16). Insulation, drywall, cabinets, countertops, flooring, fixtures. County final inspection, then a walkthrough with you where we list every punch item and close it out. The whole thing is covered by the 730-Day Done Right Promise.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Actually Shape a Detached ADU
Most of the decisions land in a short window. Here’s what you’re really picking between, with the honest trade-off on each.
- Footprint and layout: a 500 sq ft studio is the cheapest per unit and suits a rental or aging parent; 750 – 900 sq ft with a real bedroom wall costs more but rents for meaningfully more and appraises better.
- Foundation type: slab is standard and cheapest; stem-wall or raised floor costs more but gives you a place to run plumbing without trenching through cured concrete later.
- Exterior door and glazing: a solid fiberglass entry like a Therma-Tru unit handles desert sun and heat cycling better than a cheap steel door that telegraphs every temperature swing; impact-rated windows cost more upfront and cut both storm damage and summer cooling load.
- Utilities: tying into the main house’s panel and water line is the lower-cost route; a separate meter costs more but makes the unit genuinely independent if you plan to rent it.
- Roofing: tile or standing-seam metal both handle the Mojave sun well and last decades; asphalt shingle is the budget option and needs replacement sooner under this UV load.
- Finishes: a quartz counter and mid-grade cabinetry reads as a real apartment; builder-grade everything reads as a converted shed and rents accordingly.
What a New Detached ADU Costs in Paradise, NV

Plan on $45,000 – $130,000 for the structure and its systems. The low end buys a compact one-room unit with modest finishes; the high end gets you a two-bedroom with upgraded everything and separate utility service. Five things move the number:
- Size: every additional square foot carries foundation, framing, roof, and finish cost together.
- Utility strategy: tapping the main house versus running new service is a five-figure swing on some lots.
- Site conditions: sloped lots, poor drainage, or long trench runs to the connection point add grading and concrete work.
- Finish grade: cabinetry, counters, flooring, and fixtures can vary by tens of thousands across the same footprint.
- Permit scope: the county’s review fee scales with the project, and anything unusual in the plans adds review time.
A written estimate from us breaks out foundation, framing, roofing, each trade rough-in, finishes, and the permit line item separately, so you can see where the money goes and cut in the right places. Upfront pricing, no surprises: the number you see is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhy Paradise Lots and Clark County Reviews Change This Job
Paradise is unincorporated, which means a new detached ADU here goes through Clark County’s building department rather than a city counter. That single fact shapes the schedule. The county serves the whole Las Vegas Valley, so review queues are longer than what a contractor used to working strictly inside Las Vegas city limits expects, and inspections are booked through the county’s system. We build that timeline into your schedule from day one instead of discovering it mid-project.
The housing stock matters too. Around the mid-century tract homes east of the Strip and the denser apartment corridors near the airport, lots are often tighter than they look and rear setbacks get decided by a survey, not a tape measure. Add monsoon-season flash flooding and you get drainage and erosion control that has to be designed into site prep, not patched afterward. If your ADU project grows into something wider, it’s part of a full Home Additions & ADU in Paradise scope we can plan together, and homeowners often pair this with Concrete Driveways & Concrete Work in Paradise for the new parking pad and walkway, or with Paver Driveways in Paradise if they want a softer look at the entry.
We handle Home Additions & ADU work throughout Paradise and the surrounding valley, and our technicians have up to 12 years of experience with detached units specifically.
Serving Paradise, NV – Our Local Coverage Area
We serve Paradise and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: New Detached ADU in Paradise

Four to seven months from first site visit to final inspection, with the county plan review typically eating four to six weeks of that. Construction itself usually runs twelve to sixteen weeks once the permit is issued. Call (844) 797-5026 for a schedule based on your actual lot.
Yes. Because Paradise is unincorporated, the permit comes from Clark County rather than a city building department. We pull it and manage every inspection; you should never sign a contract with a builder who suggests skipping that step.
Usually not much. Most units tap the existing panel and water main, which keeps the main house untouched apart from the connection point. If your panel is already at capacity, the honest fix is an upgrade, and we’ll tell you that before the contract, not after.
Between $45,000 and $130,000 depending on size, utility strategy, site conditions, and finish grade. Call (844) 797-5026 for an exact quote. Estimates and the design consult are free.
Every ADU we build is covered by the 730-Day Done Right Promise: if it isn’t done right, we make it right. That covers workmanship for two full years, and it’s in writing.
Get a Free Estimate on Your Detached ADU
Call (844) 797-5026 to book a free on-site estimate for your new detached ADU in Paradise. A live person answers around the clock. We’ll walk the lot, talk through footprint and utility options, and leave you with a written line-item estimate and a realistic schedule. Financing is available at 0% for 18 months, and projects over $10,000 take $1,000 off.
Written by the team at Groundwork Construction Co.